Railway access road construction. Development of the Mockava terminal.

Client

UAB “Mockavos terminalas”

work place

Zelionkos village. 7, Būdvietis borough, Lazdija district. Mockava terminal

completed works

New construction of 1520/1435 mm railway tracks – 2,652 km

Installation of 1520/1435 mm switches – 4 sets.

Installation of 1520/1435 mm intersections – 2 sets.

Installation of technological crossings – 2 pcs.