NATO project of 51st kilometre of the Naujoji Vilnia–Turmantas–Latvian border line (Pazeimene)

Client

AB “LTG Infra”

Work place

Pažeimenės k., Švenčionėlių raj. sav., Pabradės sen.

Complited works

Completed design work,

About 0.9 km of railway track has been laid,

4 new spindle crossings were installed,

The existing crossing was repaired,

Alarm, communication, electricity, traffic control systems were installed.

TopRails
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.